Jun 10
We knew it was coming! The I-10 widening project started this January with minor closures, but the big changes are just ahead. In 3 weeks, all on- and off-ramps between Prince Road and 29th Street will be closed, and through traffic in that area will be reduced to 2 lanes in either direction.
What to Expect and When:
June 15 - June 22
- Over the weekend, Westbound traffic and all westbound ramps (between Prince and 29th) will be closed. All Westbound interstate traffic must exit and use the frontage roads. During weekdays, 2 lanes of traffic may pass through the construction area, but all Westbound ramps will remain closed.
June 22 - June 29
- Over the weekend, all Eastbound traffic and ramps will be closed. During weekdays, 2 lanes of through traffic will be open, but all Eastbound ramps will remain closed.
June 29 - July 1
- The interstate closes fully in both directions. All ramps are closed between Prince and 29th. All I-10 traffic must exit and use the frontage roads.
July 1 - Spring 2010 (estimated)
- All ramps, both East and West bound, are closed between Prince Roads and 29th Street. 2 lanes of through traffic will be open in both directions.
You can sign up to have updates on closures and construction sent to your email from the ADOT homepage for the I-10 widening project.